Agreement
Between Owner and Contractor
Looking
for a agreement between owner and contractor to kick-start your working
relationship on a rock-solid foundation? Then our free owner contract
form
here will fit you just fine.
Before Using Our Owner Contractor
Agreement, You Should Know These Facts
What we have here is a standard form of
agreement between owner and
contractor - It lays down the general terms and conditions of the deal,
plus sorts out what will happen in case things don't go as planned.
However everybody's situation is different and we cannot stress enough
that you must
take the time to craft and tailor this owner and contract agreement to
your exact needs. In particular, we want to draw your attention to
these finer points:
3. Date(s) of Completion
- This is where you decide whether you want the entire work project to
be recognized as one single stage, or be broken down into more
digestible chunks. For larger and longer-term projects, we will
recommend that you slice it into different stages (our owner agreement
contract allows you to spell out the payment and completion dates for
each stage).
10. Assignment -
Not referring to school homework here. Assignment affects whether the
contractor is able to "assign" this owner contractor agreement to
subcontractors. If assignment is allowed (tick the lower check box),
then the original contractor can hire subcontractors to cover part or
all of the work. That said, the contractor is still responsible for the
work standards.
* In case you are a contractor doing home improvements for homeowners
in the U.S., don't forget to attach two copies of the 3 Day Right of Recission Form to
your owner contractor agreement.
Agreement Between Owner and
Contractor
This agreement is made and entered between the Owner
_________________________ and the Contractor _________________________
on this date _______________.
The Owner and Contractor hereby agree to the following:
1. The Contractor agrees to provide all of the labor, materials and
equipment required to perform the following work for: ________________Describe Work
to be Performed_________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
as shown by the drawing(s) and/or described in the specifications
prepared by _______________ __________, which are identified by the
signatures of the parties to this agreement and become a part of this
agreement.
2. The Owner agrees to pay the Contractor the sum of $ _______________
for
the above labor, materials and equipment in the following manner:
_______________________Describe
Payment Method and Timing_______________________
______________________________________________________________________________
______________________________________________________________________________
3. The date(s) of completion shall be as follows (choose one):
[ ] The work to be performed under this
agreement between owner and contractor shall begin on _______________,
and shall be fully completed on or before _______________.
[ ] The work to be performed under this
agreement between owner and contractor shall begin on _______________,
and various portions of the above-described work shall be completed on
or before the following dates: _________Describe Work
Portions and Completion Dates________
______________________________________________________________________________
______________________________________________________________________________
4. In the event that the work is delayed due to the neglect of the
Contractor, the Contractor agrees to pay the Owner the sum of $
_______________ per day as liquidated damages until the work is
completed.
5. In the event that the work is delayed due to the neglect of the
Owner, acts of God, fire, flood, labor strikes, riots, wars and other
causes beyond the reasonable control of the Contractor, the time for
completion of the work shall be extended by the same
period as the delay occasioned by any of the aforementioned causes.
6. In the event that the Owner fails to pay any periodic or installment
payment due to the Contractor under this agreement, the Contractor may
cease work without breach pending payment or the resolution of any
dispute.
7. All changes to the work ordered by the Owner shall be in writing,
and all resulting increases or deceases in the payment sum shall be
decided by the Contractor. Any claims for increases or decreases in the
payment sum shall be presented by the Contractor to the Owner in
writing, and the written approval of the Owner must be obtained before
the Contractor can proceed with the change order.
8. The Contractor agrees to provide and pay for all labor, materials
and equipment required for the timely completion for work. The
Contractor shall employ a sufficient number of workers skilled in their
trade to perform the work. Unless otherwise specified, all materials
shall be new and of good quality.
9. All work shall be completed in a workmanship-like manner and in
compliance with all building codes and other applicable laws.
10. The Contractor agrees to re-execute any work which does not conform
to the drawings and specifications. The Contractor also warrants all
work performed, and agrees to remedy any defects resulting from faulty
materials or workmanship for a period of _____ months after work
completion.
11. Assignment for the above-described work shall be as follows (choose
one):
[ ] Neither the Owner nor Contractor shall have
the right to assign any rights or interest under this agreement between
owner and contractor without the written consent of the other. The
Contractor shall not assign any sums due, or to become due to him under
the terms of this agreement.
[ ] The Contractor may at his/her discretion
engage subcontractors to
perform the work hereunder, provided that the Contractor fully pays the
said subcontractors and remains fully responsible for the proper
completion of this work.
12. The Owner, Owner's representative(s) and public authorities shall
have access to the work at all times.
13. The Owner agrees to maintain full insurance on the above-described
work during the progress of the work, in his/her own name and that of
the Contractor. The Contractor agrees to obtain adequate insurance for
himself/herself against claims for property damages, bodily injuries
and death due to the performance of this agreement.
14. Additional Terms and Conditions:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Owner Name: ______________________________
Owner Signature:
______________________________
Date: _______________
Contractor Name: ______________________________
Contractor Signature:
______________________________
Date: _______________
Return from Agreement
Between Owner and Contractor to Contractor
Forms
|
|